Latest biomass pellet manufacturing project is in progress

complete wood pellet production line biomass fuel making pellet

1. Large production capacity 2*40 tons per hour biomass pellet plant project (Phase 1)

(1) Total budget investment: 95 million yuan

(2) Project status: construction preparation

(3) Project location: Siping City, Jilin Province

(4) Project construction details: The project covers an area of ​​6,650 square meters, with a total construction area of ​​4,000 square meters, an annual output of 100,000 tons of biomass pellets, and a treatment of 100,000 tons of straw per year.

(5) Specific progress:

①Procedures of procedures: The project is still undergoing environmental assessment procedures.

②Design completion status: The design has not yet started, and RICHI is responsible for the design.

③Civil construction: the main body has not yet started, and the specific time has not been determined.

④Equipment situation: The equipment will start production in April.

⑤Estimated project commissioning time: the end of 2021

2. Biomass straw pellet plant project

(1) Total budget investment: 1 billion yuan

(2) Project status: project approval application

(3) Project location: Chifeng City, Inner Mongolia

(4) Project construction details: The total area of ​​the project is 133,017 square meters, which is divided into two phases of construction.

(5) Specific progress:

①Procedures of procedures: Procedures of procedures: The project is undergoing preliminary procedures.

②The completion of the design: the design has not yet started, and the specific start-up time has not yet been determined.

③Civil construction: the main project has not been constructed yet, and the construction unit has not yet been determined.

④Equipment situation: The equipment will start production in June.

⑤Estimated project commissioning time: April 2022

3.Complete 20tph straw pellet processing factory project

(1) Total budget investment: 397,836,900 yuan

(2) Project status: engineering design

(3) Project location: Tonghua City, Jilin Province

(4) Details of project construction: The total area of ​​the project is 3900 square meters, which is divided into two phases of construction.

(5) Specific progress:

①Procedures of procedures: Procedures of procedures: The project is undergoing environmental assessment procedures.

②Design completion status: Preliminary design will be carried out simultaneously, and RICHI will be responsible.

③Civil construction status: The main project has not yet been constructed, and bidding will be invited later.

④Equipment situation: The equipment will start production in May.

⑤Estimated project commissioning time: the end of 2021