In China, it is necessary to select the site of the pig farm before the pig is raised. However, after the address of the pig farm is selected, the construction of the pig farm cannot be done immediately. Instead, a process is required. This process is called a pig farm application. The environmental assessment operation procedure, the construction of the pig farm can only be started after this procedure, the specific procedure and operation method are listed as follows:

positive impact of compound pig animal feed processing plant

1. Application conditions

(1) The site selection conforms to the overall urban planning or the construction planning of villages and towns, and conforms to the requirements of environmental function planning and overall land use planning;

(2) Comply with national agricultural policy;

(3) Meet the requirements of cleaner production;

(4) The pollutants discharged do not exceed the pollutant discharge standards set by the state and the province;

(5) Key pollutants meet the requirements of problem control;

(6) Entrust a qualified unit to prepare the project environmental impact assessment documents.

2. Information to be submitted

(1) Preparation of Environmental Impact Assessment Report Project

①The application report for environmental protection approval of the project;

②Project registration certificate issued by the development and reform or economic and information department;

③Project environmental impact report;

④The evaluation opinions issued by the Environmental Technology Center on the project;

⑤Infrastructure projects need to provide planning permits and red line diagrams;

⑥If it involves water and soil conservation, issue the opinion of the water conservancy administration department; if it involves farmland protection area, issue the opinion of the agriculture and land administration department; if it involves the protection of aquatic animals, issue the opinion of the fishery administration department; it involves nature reserves Yes, issue the opinion of the competent forestry authority.

⑦Other materials required by the environmental protection department.

(2) Preparation of Environmental Impact Assessment Report Form Project

①The application report for environmental protection approval of the project;

②Project registration certificate issued by the development and reform or economic and information department;

③Project environmental impact report form;

④The evaluation opinions issued by the Environmental Technology Center on the project;

⑤Infrastructure projects need to provide planning permission and red line diagram;

⑥If it involves water and soil conservation, issue the opinion of the water conservancy administration department; if it involves farmland protection area, issue the opinion of the agriculture and land administration department; if it involves the protection of aquatic animals, issue the opinion of the fishery administration department; it involves nature reserves Yes, issue the opinion of the competent forestry authority.

⑦Other materials required by the environmental protection department.

[More info about pig]

How should small and medium-sized feed mills deal with the downturn in pig prices?

Poor market conditions, what should the pig feed factory do?

¿Qué equipos se necesitan para montar una planta de procesamiento de piensos para aves de corral, pollos, patos y cerdos??

Cómo construir una línea de producción de pellets de piensos combinados de alta calidad para pollos de engorde y cerdos?

Producción anual de 40.000 toneladas de ganado vacuno y porcino planta de procesamiento de piensos propuesta de negocio

Turnkey animal feed project proposal of 10000t/a pig animal feed pellet production plant factory for premix and concentrated feed

correo electrónico
whatsapp
haz clic
Ir arriba